by Technological | Aug 12, 2020 |
Mishor Rotem Power Station. OPC Rotem Ltd. 440 MW Combined Cycle Natural Gas – fired Power Plant. (2012 – 2013). Providing QA/QC Services to the project’s main construction contractor – Isa Khoury Metal Industry Ltd. Establishmentand management of QA/QC process;...
by Technological | Aug 12, 2020 |
Dorad Power Station, Ashkelon. Dorad Energy Ltd. (2012 – 2014). 840 MW Combined Cycle Natural Gas – fired Power Plant. Providing Owner’s Engineering Services in the fields of Mechanical and Electrical Engineering, Welding, Quality Assurance and Quality Control....
by Technological | Jul 17, 2020 |
Pipelines (INGL) Ltd. (2012 – 2014). Providing QA/QC and inspection services to main contractor – Brand Industries / TMNG Ltd. for re-organization and improvement of project QA/QC and inspection activities. Preparationof QA/QC procedures;...
by Technological | Jul 17, 2020 |
55 MW Combined Cycle Natural gas-fired Power Plant. Providing QA/QC, inspection and licensing services to project’s EPC contractor – M+W Israel: Establishmentand management of QA/QC process; On– site inspection of the mechanical works and connection to the Natural Gas...
by Technological | Jul 17, 2020 |
120 MW Combined Cycle Natural Gas – fired Power Plant. Providing QA/QC, inspection and licensing services to project’s EPC contractor – M+W Israel: Establishmentand management of QA/QC process; On– site inspection of the mechanical works and connection to the Natural...